Goodyear Pipelines

In collaboration with CH2M/Jacobs, Hunter Contracting Co. successfully completed an award-winning project involving the installation of over seven miles of waterline. The project demanded exceptional efficiency as it required coordination with multiple jurisdictions and numerous utility crossings. To meet the ambitious timeline, three mainline crews and one underground subcontractor worked simultaneously, each contributing to different phases of the project. The scope of work encompassed various types of waterline, including 37,000 LF of 24-inch C-900 waterline, 2,500 LF of 24-inch.

Client:
CH2M/Jacobs
Completion:
November 2021
Delivery Method:
DB
Cost:
$13.5M
  • 2,500 LF of 24-inch Ductile iron waterline installation
  • 37,000 LF of 24-inch C-900 Waterline installation
  • 3-inch Air release valves (5)
  • 4,800 LF of 28-inch fused HDPE through the Agua Fria River crossing
  • 5,400 SY of Restoration paving 
  • 6-inch Air release valves (8)
  • 100,000 CY of Mass excavation for open cut excavation through the Agua Fria River Crossing
  • Accessways (5)
  • Blow-off assemblies (5)
  • Clear and Grub
  • Concrete HDPE anchors (2)

AWARDS

 

 
 Design-Build Institute of America (DBIA) 

2022 National Project / Team Award


Arizona Chapter of American Council of Engineering (ACEC) 

2022 ACEC Grand Award