SAS Retention Pond

Hunter Contracting Co. (Hunter) built the new Scottsdale Auto Show (SAS) retention pond to hold tailwater and fill in the old pond for the land to be sold by a developer. The land had the community's old irrigation tailwater pond that consisted of two ponds with one vertical turbine pump. The project consisted of clearing out grubs, trees, bushes, and weeds. Hunter removed old vertical turbine pumps and associated steel piping that put the tailwater back into circulation. Our team then rebuilt the area with a new excavation retention pond across the street.

Client:
MayDall Construction/SRP-MIC
Completion:
May 2019
Delivery Method:
CMAR
Design Engineer:
Kimley-Horn
Cost:
$4.6M
  • 400 HP vertical turbine pump installation
  • Chainlink fencing around new pond installation
  • Decomposed granite around the perimeter of pump installation
  • Electrical components for pump installation
  • Headwalls and turnout structure construction
  • Pond lining system installation
  • PVC and RCP piping installation
  • Screen 0.5-inch
  • Shade structures installation
  • Spillways and overflow weir construction
  • Wet well structure construction