Grand Village Lift Station

The overall project consisted of installing two (2) 182 gpm non-clog sewage pumps, dual 4-inch force mains, gravity sewer, and electrical equipment and controls. In general, the work includes furnishing all labor, materials, and equipment for construction of the lift station and appurtenances and site facilities, including a pad for future odor control, emergency generator, and site lighting.

Client:
Garrett-Walker Homes
Completion:
March 2020
Delivery Method:
DBB
Design Engineer:
Coe & Van Loo
Cost:
$857k
  • Access drive
  • Back-up generator
  • Electrical and instrumentation
  • Grading and earthwork
  • Gravity server tie-in
  • Hybrid cast-in-place/precast wet well
  •  Magnetic flowmeter
  • Manholes
  • Masonry site wall
  • MOPOs
  • SCADA and control
  • Submersible pump