Phoenix Division Projects

CM@Risk Indian Bend Wash

This project includes one mile of four lanes of full roadway reconstruction including: signalized intersections of arterial roadway, and a ten-cell concrete arch-bridge structure, drop structures, retaining walls and other artistic elements within the wash. Recreational areas are also incorporated into the work. Public art on the north side of the bridge and drop structure is to include 5 Gargoyle Horses spaced about 125-feet apart and set on 3-foot wide dark gray colored concrete with a sand-blasted “plinths” built into the drop structure. The top of the plinths will form a trough to carry the water to the horse gargoyle. At night, the horse gargoyles will be elegantly up lit with blue lights on the east side and yellow lights on the west side. Public art on the south side of the bridge consists of six ‘stadia walls’ located in the basin between the bridge columns and flow berms. The walls step in different ways at one foot vertical increments forming various patterns in the water as it rises during flow events. To mark these changing water elevations, inset bands of one-inch red tiles circumscribe each wall

 
 
Arcadia Pedestrian Bridge at 48th Street and Indian School at SRP Portals and Loops Trail Improvements

The City of Phoenix and SRP have designated the Arizona Canal as part of the SRP Portals and Loop 11 mile trail system.  This site was in need of a safe, ADA compliant access at the canal crossing.  HCC was hired through a Job Order Contract to install an owner provided pedestrian bridge to complete the trail crossing.  HCC restored the owner provided bridge by sandblasting, painting and installing a new concrete deck surface.  HCC coordinated with SRP Irrigation and Power in establishing a work plan to construct the bridge's 30ft shaft foundations, abutments, approaches and bridge erecting plan.

 

After coordination with 3 crane companies, it was determined that crane picks were not feasible. HCC implemented an engineered, low-clearance pick using two excavators. HCC worked closely with the City in keeping the Arcadia District informed of the construction operations to minimize disturbance of resident's daily activities.
 
 
43rd Avenue Pedestrian/Bicycle Underpass
This heavily traffic congested area made bicycling and pedestrian crossing an unsafe environment. HCC removed the hazards by installation of a pre-cast 10 ft x 10 ft bicycle/pedestrian underpass under 43rd Avenue and Peoria Avenue.
 
 
29th Avenue Pedestrian/Bicycle Underpass
Heavy volume of traffic around Metro Center resulted in the construction of pre-cast 10 ft x 10 ft bicycle/pedestrian underpass under 29th Avenue at Metro Center. Additional work elements include concrete cast in place access ramps, electrical, water and storm drain relocations, concrete and asphalt paving, landscaping, and traffic control.
 
 
CM @ Risk Baseline Road
Booming new retail development on both sides of the roadway lead to heavy volumes of traffic. This project was to reconstruct portions of existing 2 mile roadway; add raised medians with street lighting and landscaping. Install underground SRP Irrigation, Install 16” waterline, Widen existing bridge over SRP Canal, rubber overlay entire section and stripe. Worked closely with Entranco Engineering to develop over $250,000 in cost savings.
 
 
Scottsdale Road (Con-Arch)
Reconstruct existing 2 mile roadway from four lanes to six. Work elements included relocating 69KV overhead to underground. Installation of water, sewer, and storm drain. Construct Bridge (Value Engineering redesign to Con-Arch). Extensive phasing, traffic signals, accelerated schedule to meet Resort requirements, full depth reconstruction at 4 intersections.
 
 
GRIC 48th Street & Maricopa Road
Multi phased road project to provide additional access to the Wild Horse Casino. First phase of work required close coordination with adjacent contractors to ensure a timely completion.
Status of Project: Phase I Completed
 
 
Gila River Indian Community Subdivisions
Guaranteed Maximum Price Contract for construction of three subdivision infrastructures for the Gila River Indian Community. This project required extensive plan evaluations during the bidding phase. Extensive partnering and coordination was required to develop the joint trench design for gas, electrical, and street lighting.
 
 
Queen Valley Box and Roadway
Constructed for Pinal County
 
 
Union Hills Bridge at New River
Widen existing bridge an additional 14 feet to allow for construction of an additional turn lane at Union Hills Drive and the 101.The existing bridge was constructed in 1995 by Hunter Contracting Co for MCDOT.
 
 
Dynamite Road
This technically challenging project provided upgraded valve control and connections to the 36” City of Phoenix Cave Creek Water Facilities. Deep excavations were required in the intersection of Dynamite Road and Cave Creek to allow for the installation of the 36” tapping sleeve and valve.
 
 
SRP San Tan Warner Road Pipeline Installation

Installation of 24,000 LF of SDR 11 HDPE Pipe for Cooling water Discharge. Pipe ran from Warner Road East of Val Vista Road to Power Road. (over 5 miles). Work involved maintaining continuously high volumes of traffic, Specialized Boring done at intersections to facilitate traffic, keeping the intersections open and minimize traffic congestion. Special Night work operations, fusion weld pipe, back fill with slurry. Milling and pavement replacement.

 
 
Cardinal Stadium Water, Sewer, Storm Drain

HCC has been providing preconstruction services to Hunt for much of the remaining site work at the stadium.This includes plan reviews and pricing for the underground water, storm drain, grading, paving and bridge work at 95th Avenue. To date HCC has been awarded a construction contract for water, sewer and storm drain and is currently installing this work and is pursuing negotiations for remaining work.

 
 

Yuma – Casa Grande Highway

(I-8) Mohawk Canal Overpass, EB & WB 

Remove and replace existing bridges on Interstate 8 Mohawk Canal. New bridge structure consisted of Post Tensioned box girder end spans with Pre stressed Type 4 Girders.

   
 
 
 

 

Home | Company | Specialties | Projects | Subcontractors | Careers | Contact
Copyright © 2005 Hunter Contracting Company