Scope of Work

Replace the existing water cooled chillers with air cooled chillers
Demolition of the existing equipment and piping which was replaced
Replace the Energy Management System / Control System with an Automated Logic Direct Digital Control (DDC) system

Replace chilled water pumps, control valves, valve operators, damper operators, duct detectors, cooling coils, resistance heater and controllers and other chilled water piping devices as needed

OWNER

Central Arizona Project (CAP)

DELIVERY METHOD

CMAR

CONTRACT AMOUNT

$ 2.5 Million